Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009 and FEP-03/364/2009 Monthly Environmental Monitoring
& Audit Report
- SEPTEMBeR
2010 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
5 October 2010 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
6.3 Review of the Reasons for and the Implications of
Non-compliance
6.4 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts under
the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.3 Summary of submission status under
FEP-03/364/2009 Condition
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Table 3.5 Summary of submission status under
EP-364/2009/A Condition
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.7 Summary of submission status under
FEP-02/364/2009 Condition
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.9 Summary of submission status under
FEP-01/364/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Air Monitoring Station
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract
no. 04/HY/2006
Table 5.3 Noise Monitoring Station for Contract
nos. HK/2009/01 and HK/2009/02
Table 5.4 Air Monitoring Stations for Contract no.
HY/2009/17
Table 5.5 Air Monitoring Stations for Contract no.
04/HY/2006
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Details of Waste Disposal for Contract no.
HY/2009/17
Table 5.9 Details of Waste Disposal for Contract
no. 04/HY/2006
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/17
Table 8.2 Summary of Environmental Inspections for
Contract no. 04/HY/2006
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation
Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17
- Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Mobilization and plant setup for site
preparation work.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
·
Modification of bus bays at the bus terminus;
·
Widening of carriageway at the bus terminus;
and
·
Relocation of existing lay-bay at Man Kwong
Street
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009 under
FEP-02/364/2009
·
No major construction activity was undertaken in
reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activity was undertaken in
reporting month.
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Drilling, installation steel H-Pile &
grouting
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
·
Modification of bus bays at the bus terminus;
·
Widening of carriageway at the bus terminus;
and
·
Relocation of existing lay-bay at Man Kwong
Street
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No major construction activities are anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activities are anticipated in coming reporting month.
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009
and FEP-03/364/2009
to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.3 of EM&A Manual
and “Environmental Monitoring and Audit
Requirements”
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works for
Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP)
nos. FEP-01-364/2009, FEP-02/364/2009 and FEP-03/364/2009 during the period 28th August to 27th September
2010. The
cut-off date of reporting is at 27th of each reporting month.
Section 1 Introduction
– details the scope and structure of the report.
Section 2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of Regulatory Compliance
– summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4 Monitoring
Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance
Audit – summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link”
(hereafter called “the Project”) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of
Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project
involves the construction and operation of a trunk road and its road tunnel
more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses
existing developments from Central to North Point. The
scope of the Central-Wanchai
Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
·
A dual three-lane trunk
road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length
defined from the connection with the existing Rumsey Street Flyover in Central,
through to a connection with the existing Island Eastern Corridor to the east
of the Causeway Bay Typhoon Shelter(CBTS);
·
The Central Interchange
near the Rumsey Street Flyover to provide road connections to the Central area;
·
Tunnel control buildings
and ventilation buildings;
·
Slip roads to connect the
CWB to the local road system in the Wan Chai North and Causeway Bay area;
·
Associated road lighting,
road signing, traffic control and surveillance system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting month, the
construction works for Contracts no. 04/HY/2006 was commenced in mid-September
2010. Advance piling work at
FEHD Whitfield Depot under Contract no. HY/2009/17 is anticipated to be
commenced in early of October 2010. The details of individual contracts are summarized in
Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
Early of October 2010 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre - Tunnel Works |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) (CWB Tunnel) |
DP1 |
Pending |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principle Resident Engineer |
Mr. Frankie Fan |
2607 7801 |
2687 2322 |
Engineer for CWB |
Principle Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Daniel Chan |
9372 0495 |
|||
Environmental Officer |
Mr. Andy Mak |
6461 3065 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Ken Yang |
9262 6791 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In the reporting month,
the principal work activities of individual contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under EP-364/2009/A
·
Modification of bus bays at the bus terminus;
·
Widening of carriageway at the bus terminus;
and
·
Relocation of existing lay-bay at Man Kwong
Street
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Mobilization & Plant setup for site
preparation work.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
·
No major construction activity was undertaken
in reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction activity was undertaken
in reporting month.
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
·
Modification of bus bays at the bus terminus;
·
Widening of carriageway at the bus terminus;
and
·
Relocation of existing lay-bay at Man Kwong
Street
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Drilling, installation of steel H-Pile and
grouting.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No major construction activity is anticipated in
coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activity is anticipated in
coming reporting month.
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the
status of permits and/or licences under the individual contract(s) are
presented as below:
Contract
no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-03/364/2009 for
contract no. HY/2009/17 are shown
in Table
3.2 and
Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31
Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 May 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18
September 2010 |
Conditions 2.7 and 2.8 |
Submission
of works schedule and location plan |
1 September 2010 |
Condition
2.9 |
Noise Management
Plan |
1
September 2010 |
Contract
no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under EP-364/2009/A
3.1.4.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under EP-364/2009/A for contract no. 04/HY/2006 are shown
in Table
3.4 and
Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
N/A |
N/A |
N/A |
Construction Noise Permit (CNP) for piling equipment |
Construction Noise Permit (CNP) for non-piling equipment |
N/A |
N/A |
N/A |
Construction Noise Permit (CNP) for non-piling equipment |
Discharge Licence |
N/A |
N/A |
N/A |
Discharge Licence |
Registration as a Waste Producer |
7005123 |
9 March 2007 |
N/A |
Registration as a Waste Producer |
3.1.5.
Contractor is strongly
reminded that the Notification of Works under Air Pollution Control Ordinance
and other necessary submission shall be submitted to EPD and copied to the
Engineer timely during the work preparation stage.
Table 3.5 Summary
of submission status under EP-364/2009/A Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 June 2010 |
Conditions 2.7 and 2.8 |
Submission of
works schedule and location plan |
11 June 2010
and 5 August 2010 |
Condition
2.9 |
Noise Management
Plan |
End
of September 2010 |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
3.1.6.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-02/364/2009 for
contract no.
HK/2009/01 are shown in Table 3.6 and
Table 3.7
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Registration as a Waste Producer |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-02/364/2009 Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-01/364/2009 for
contract no.
HK/2009/02 are shown in Table 3.8 and
Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31
Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30
Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31
Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
Billing Account under Waste
Disposal Ordinance |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Table 3.9 Summary
of submission status under FEP-01/364/2009 Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
3.1.8.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and
Figure 4.1.
Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table
4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
4.1.2.
Reviewed the past
monitoring results and observation at Station M4a, the monitoring location at
Causeway Bay Community Centre is facing and closed to the Island Eastern
Corridor. Traffic noise is the major noise source obtained in the monitoring
that cannot be reflected the fact of the construction noise from the
construction site. Victoria Centre (Station ID: M4b) is proposed as alternative
noise monitoring station, which is more appropriate and representative as noise
monitoring station for monitoring the construction noise arising from the near
construction site.
Noise Monitoring Parameters, Frequency
and Duration
4.1.3.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One set of measurements between 0700 and 1900
hours on normal weekdays.
4.1.5.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.8.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.2 and Figure 4.1.
Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
MA1e |
International
Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International
Finance Centre (western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and
Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute adjustable flow
range;
·
Equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
Capable of providing a minimum exposed area
of 406 cm2;
·
Flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
·
Equipped with a shelter to protect the filter
and sampler;
·
Incorporated with an electronic mass flow
rate controller or other equivalent devices;
·
Equipped with a flow recorder for continuous
monitoring;
·
Provided with a peaked roof inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8" x 10" shall
be labeled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
4.2.10. All
the collected samples shall be kept in a good condition for 6 months before
disposal.
4.2.11. Current
calibration certificates of equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. 04/HY/2006 –Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street.
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix
5.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.2.
Since only site preparation works was
undertaken during the reporting month, no noise monitoring was conducted.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
5.1.3.
The proposed division of noise monitoring
stations for Contract no. 04/HY/2006 are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. 04/HY/2006
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
5.1.4.
Daytime noise monitoring at stations M7e and
M7w were commenced on 30 August 2010. No exceedance was recorded in the
reporting month. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
and Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5.
The commencement of construction works for
Contract no. HK/2009/01 and HK/2009/02 under FEP-02/364/2009 and
FEP-01/364/2009 respectively are pending. The proposed division of noise
monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works
5.2.1.
The proposed division of air monitoring
stations are summarized in Table 5.4 below. Air monitoring for
the piling works under contract no. HY/2009/17 is anticipated to be commenced
in the early of October 2010.
Table 5.4
Air
Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
CMA2a |
Causeway Bay Community Centre |
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
5.2.2.
The proposed division of air monitoring
stations are summarized in Table 5.5 below.
Table 5.5
Air
Monitoring Stations for Contract no. 04/HY/2006
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.2.3.
Air quality monitoring at MA1e and MA1w were
commenced on 9 September 2010. No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
5.2.4.
Air quality
monitoring will be commenced
depending on the commencement of work for Contract no. HK/2009/01 under
FEP-02/364/2009.
The proposed division of air monitoring stations are summarized in Table
5.6 below.
Table 5.6
Air
Monitoring Stations
for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
AECOM site office at Work Area 1 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.2.5.
Air quality
monitoring will be commenced
depending on the commencement of work for Contract no. HK/2009/02 under
FEP-01/364/2009.
The proposed division of air monitoring stations are summarized in Table
5.7 below.
Table 5.7
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works
5.3.1.
No inert and non-inert C&D waste was disposed
of for the site preparation works in the reporting month. Details of the waste
flow table are summarized in Table 5.8.
Table 5.8 Details
of Waste Disposal for Contract no. HY/2009/17
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under EP-364/2009/A
5.3.2.
Inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.9.
Table 5.9 Details
of Waste Disposal for Contract no. 04/HY/2006
Inert C&D materials disposed |
170m3 |
170m3 |
Chai Wan T.K.O. 137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
5.3.3.
No inert and non-inert C&D waste was disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.10.
Table
5.10 Details
of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.4.
No inert and no-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.11.
Table
5.11 Details
of Waste Disposal for Contract no. HK/2009/02
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works
6.1.1.
No noise monitoring was
undertaken in the reporting month.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
6.1.2.
Noise monitoring at M7e and M7w were
commenced on 30 August 2010. No exceedance was recorded in the reporting month.
Contract nos. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
6.1.3.
No noise monitoring was
undertaken in the reporting month.
Contract no. HY/2009/17 –Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
6.2.1.
No air quality monitoring
was undertaken in the reporting month.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
EP-364/2009/A
6.2.2.
Air quality monitoring at MA1e and MA1w were
commenced on 9 September 2010. No exceedance was recorded in the reporting
month.
Contract nos. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works and
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
6.2.3.
No air quality monitoring
was undertaken in the reporting month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from
monitoring was recorded in the reporting month.
6.4.1.
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4 of the EP-364/2009/A,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WWDII), Central-WanChai
Bypass (CWB) and Island Eastern Corridor Link projects (IECL).
7.0.2.
From the Monthly EM&A report (August
2010) of Central Reclamation Phase III the key works in September 2010 are as
follows:
·
Type A filling in FRAW and
FRAE above +2.5mPD
·
General filling works
above +2.5mPD in IRAE
·
Surcharging in FRAW and
FRAE
·
Construction of cantilever
slab at caisson
·
Pile cap and base slab
construction at Culvert F
·
Construction of storm and
foul drainage and gullies in hinterlands for Road P2, Road D7, and Road D9
·
Construction of watermains
at Road D7
·
Road P2 Underpass ramp
structures
·
Precasting for retaining
wall (offsite)
·
Installation of cooling
water mains for Tamar Development Project
·
Installation of cooling
mains discharge pipes in FRAE
·
Diaphragm wall and
barrettes for CWB Works
·
Excavation to formation
level at CWB works
·
Construction of CWB
structure
·
Disposal of material off-site to Government
fill banks
7.0.3.
According to the construction programme of Wan
Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor
Link projects, the major construction activity under Wan Chai Development Phase
II was the dredging works at North Point Reclamation Stage 1(NPR1), Wan Chai
Reclamation Stage 1(WCR1) and cross-harbour water mains in the reporting month.
The major environmental impact was water quality impact at North Point and Wan
Chai. Land-based construction activity was only the modification works of bus
terminus near Man Yiu Street and Man Kwong Street under CWB in the reporting
month.
7.0.4.
The major environmental impacts generated from
the Central Reclamation Phase III were located along the coastline of Central
and Admiralty while only modification works of bus terminus near Man Yiu Street and Man Kwong Street
under CWB was undertaken in the reporting month. Since the modification of bus
terminus was still under initial stage, no significant air and noise impact
were anticipated in the reporting month. Besides, no environmental monitoring
exceedance was recorded from the Project in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was insignificant.
.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/17 and
04/HY/2009. No non-conformance was identified during the site audits.
8.0.2.
Two site inspections for Contract no.
HY/2009/17 were carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table
8.1 Summary
of Environmental Inspections for
Contract no. HY/2009/17
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
100915_01 |
15-Sep-10 |
Mud is observed in U-Channel. The contractor is reminded to
clear it and place sand bags to prevent blocking. |
Clear the mud. |
Completion
as observed on 22-Sep-10 |
100915_02 |
15-Sep-10 |
EP should be placed on all exits of construction
site |
Place EP on all exits. |
Completion
as observed on 22-Sep-10 |
100922_01 |
22-Sep-10 |
All holes shall be blocked to prevent any water
leakage from the construction site / water shall be pumped out |
Block all holes in the construction site |
Completion
as observed on 28-Sep-10 |
8.0.3.
Four site inspections
for Contract no. 04/HY/2006 were carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. 04/HY/2006
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
100910_1 |
09-Sep-10 |
The contractor is reminded to
place sand bags at the exits of the construction site |
Place sand bags at the exits of the construction site |
Completion
as observed on 13-Sep-10 |
100910_2 |
09-Sep-10 |
The contractor is reminded to cover all gullies in the area of the construction site |
Cover all gullies at the area of construction site |
Completion
as observed on 13-Sep-10 |
100910_3 |
09-Sep-10 |
The contractor is reminded to provide of designated
chemical waste storage area. |
Cover all chemical waste containers. |
Completion
as observed on 13-Sep-10 |
100913_01 |
13-Sep-10 |
Sand & mud escaped outside the water barrier
along Man Kong Street need to be cleaned |
Place sand bags at the barrier of the construction site |
Completion as
observed on 20-Sep-10 |
100913_02 |
13-Sep-10 |
Refuse storage point housekeeping need to be
improved |
Improve housekeeping for point of refuse storage |
Completion
as observed on 20-Sep-10 |
100920_01 |
20-Sep-10 |
Gullies/ drainage U Channel shall be covered well to prevent sand and stone
accumulation |
Cover all U Channel |
Completion
as observed on 27-Sep-10 |
100927_01 |
27-Sep-10 |
Manhole shall be covered to prevent any sand and
stone feed
into the drainage system |
Cover the manhole |
Completion
as observed on 4-Oct-10 |
9.0.1.
No complaint, notification
of summons and prosecution was received in the reporting month. The details of
cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1.
9.0.2.
Cumulative statistic on complaints and
successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
September 2010 |
0 |
Project-to-Date |
0 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table
10.1 Summary of Key Construction
Activities of Individual Contract(s) to be commenced in Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/17 |
·
Drilling, installation
steel H-Pile & grouting |
·
Noise barrier shall be implement ·
Watering any dust generating activities |
04/HY/2006 |
·
Modification of bus
bays at the bus terminus ·
Widening of carriageway
at the bus terminus ·
Relocation of existing lay-bay at Man Kwong Street |
·
Noise barrier shall be implement ·
Watering any dust generating activities |